Work operations planned from March 15 to 21, 2019

5 months ago

SAINTE-CATHERINE OUEST PROJECT

• Reconstruction of underground infrastructures
• Rue Sainte-Catherine Ouest, between Boulevard Robert-Bourassa and Rue De Bleury
• Since February 11, 2019

WORK SCHEDULE - 24/7***
Since March 11, the work operations for the Sainte-Catherine Ouest project have been performed 24 hours a day, seven days week, unless indicated otherwise. The work schedule may change, depending on the weather conditions and unforeseen circumstances.



WORK ZONE: WEST LOT

RUE SAINTE-CATHERINE OUEST, BETWEEN BOULEVARD ROBERT-BOURASSA AND RUE SAINT-ALEXANDRE


Corner of Boulevard Robert-Bourassa


Nature of the work: sewer reconstruction
Expected impacts: excavator noise, hydro-excavation
Dates and schedule: March 15 to 21 (around the clock)
Between Boulevard Robert-Bourassa and Rue Union

Nature of the work: demolition and reconstruction of underground telecommunications infrastructures
Expected impacts: hydraulic drilling, sawing, nailing
Dates and schedule: March 20 and 21 (6 a.m. to 3 p.m. - 3:30 p.m. to 12:30 a.m.)

Corner Rue Union

Nature of the work: reconstruction of sewers and the water supply system
Expected impacts: excavator noise, vibration, sawing, steamroller
Dates and schedule: March 15, 16, 17 (around the clock)

Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, sawing, nailing
Dates and schedule: March 18, 19, 20, 21 (6 a.m. to 3 p.m. - 3:30 p.m. to 12:30 a.m.)

Between Rue Union and Place Phillips

Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, sawing, nailing
Dates and schedule: March 15 (6 a.m. to 3 p.m. - 3:30 p.m. to 12:30 a.m.), 16 and 17 (6 a.m. to 3 p.m.)

Nature of the work: reconstruction of the water supply system and sewers
Expected impacts: excavator noise, vibration, sawing, steamroller
Dates and schedule: March 18, 19, 20, 21 (around the clock)

Corner of Rue City Councillors

Nature of the work: sewer reconstruction
Expected impacts: excavator noise, hydro-excavation
Dates and schedule: March 15 to 21 (around the clock)

Between Rue City Councillors and Rue Saint-Alexandre

Nature of the work: demolition of underground electrical infrastructures
Expected impacts: hydraulic drilling, sawing, nailing
Dates and schedule: March 15, 18, 19, 20, 21 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.), 16 and 17 (6 a.m. to 3 p.m.)

________________________________________________________________________________________________________________________________________________


WORK ZONE: EAST LOT

RUE SAINTE-CATHERINE OUEST, BETWEEN RUE SAINT-ALEXANDRE AND RUE DE BLEURY


Corner Rue Saint-Alexandre


Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, hydro-excavation, sawing, nailing
Dates and schedule: March 15 to 21 (6 a.m. to 3 p.m.)

Nature of the work: reconstruction of water mains
Expected impacts: excavator noise, vibration, sawing, steamroller
Dates and schedule: March 15 to 17 (around the clock)
Between Rue Saint-Alexandre and Rue De Bleury

Nature of the work: installation of water mains and service connections
Expected impacts: excavator noise, hydraulic drilling (day and evening only), hydro-excavation
Dates and schedule: March 15 to 21 (around the clock)

Corner Rue De Bleury

Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, hydro-excavation, sawing, nailing
Dates and schedule: March 15 to 21 (6 a.m. to 3 p.m.)

___________________________________________________________________________________________________________________________


STAY INFORMED

Have a question you would like to ask?

Contact our liaison officers between 7:30 a.m. and 9 p.m. at 514-867-9339 or stecatherineouest@ville.montreal.qc.ca

FACILITATE YOUR TRAVEL

Mobilité Montréal

PARKING NEAR THE WORK SITE

Valet service
Drop-off locations are on the corner of Rue Sainte-Catherine Ouest and Rue Mansfield (west), and on the corner of Boulevard De Maisonneuve and Rue De Bleury (north).

City Parking application
Reserve a private parking space, underground or outdoors, at a preferential rate.

Delivery zones

___________________________________________________________________________________________________________________________