Relocation of public utilities for the construction of the REM station McGill

9 months ago

At the De Maisonneuve West and McGill College intersection
Beginning late September, for approximately one month Weekends, day and night

In preparation for the construction of the future station McGill, the public utilities (sewer, water main, telecommunications network) located on De Maisonneuve West, at the McGill College Avenue intersection, must be relocated. This majority of the work will take place on weekends. To speed up work and minimize the impact on the sector, work blitz periods will take place during the day and night.

Due to the complex nature of the work to be performed, the first intervention may cause additional disruptions during the week. Beginning no earlier than Thursday, September 28, these will last no longer than two days. The other targeted weekends are as follows:

- From Friday, October 5 (after the evening rush hour) to Tuesday, October 9 (before the morning rush hour)
- From Friday, October 12 (after the evening rush hour) to Monday, October 15 (before the morning rush hour)

All businesses and office towers will remain accessible during the work, as will the Montréal Eaton Centre parking lot and loading dock.