Work operations planned from March 29 to April 4, 2019

2 months ago

SAINTE-CATHERINE OUEST PROJECT

  • Reconstruction of underground infrastructures
  • Phase 1, lot 1 A: between Boulevard Robert-Bourassa and Rue De Bleury
  • February 11 until the fall of 2019. Development work from 2019 to 2020
  • Work schedule: 24/7, unless indicated otherwise


All businesses will remain open during the work operations.

________________________________________________________________________________________________________________________________________________


**Traffic in the area**

As part of the work on the REM’s future McGill station, starting on April 1 and until the fall of 2019, car traffic will be reduced to a single lane southbound, on the west side of Avenue McGill College. Northbound traffic will be interrupted between Rue Sainte-Catherine Ouest and Rue Cathcart.

________________________________________________________________________________________________________________________________________________


WEST LOT – WORK ZONE

RUE SAINTE-CATHERINE OUEST, BETWEEN BOULEVARD ROBERT-BOURASSA AND RUE SAINT-ALEXANDRE

The work schedule may change, depending on the weather conditions and unforeseen circumstances.


Corner Boulevard Robert-Bourassa


Nature of the work: sewer reconstruction
Expected impact: excavation noise
Dates and schedule: March 29, 30 and 31 (around the clock)

Nature of the work: reconstruction of sewers and water supply system
Expected impacts: excavator noise and water service interruptions*
Dates and schedule: April 1, 2, 3 and 4 (around the clock, except water service interruptions)

*Planned water service interruptions:

Zone concerned: Boulevard Robert-Bourassa, between Rue Sainte-Catherine Ouest and Rue De Maisonneuve Ouest

- Overnight from April 1 to 2 (10 p.m. to 6 a.m.)
- Overnight from April 2 to 3 (10 p.m. to 6 a.m.)


Between Boulevard Robert-Bourassa and Rue Union

Nature of the work: demolition and reconstruction of underground telecommunications infrastructures
Expected impacts: hydraulic drilling, excavation, sawing
Dates and schedule: March 29 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.), March 30 and 31 (6 a.m. to 3 p.m.)

Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, excavation, sawing
Dates and schedule: April 1, 2, 3 and 4 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.)

Corner Rue Union (south side)

Nature of the work: reconstruction of underground electrical infrastructures
Expected impacts: wood sawing, nailing
Dates and schedule: March 29, April 1, 2, 3 and 4 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.) March 30 and 31 (6 a.m. to 3 p.m.)

*Planned water service interruptions:

Zone concerned: Rue Union, between Rue Sainte-Catherine Ouest and Boulevard De Maisonneuve Ouest

- Overnight from April 3 to 4 (10 p.m. to 6 a.m.)
- Overnight from April 4 to 5 (10 p.m. to 6 a.m.)

Between Rue Union and Place Phillips

Nature of the work: installation of water mains
Expected impact: excavator noise
Dates and schedule: March 29, 30 and 31 (around the clock)

Nature of the work: test trenches for soil sampling
Expected impact: excavator noise
Dates and schedule: March 29 (overnight)

Between Rue City Councillors and Rue Saint-Alexandre

Nature of the work: reconstruction of underground electrical infrastructures
Expected impact: noise
Dates and schedule: March 29, 30, 31, April 1, 2, 3 and 4 (6 a.m. to 3 p.m.)

Nature of the work: installation of underground infrastructures to temporary connect the old water mains to the new water mains
Expected impact: noise
Dates and schedule: April 1 and 2 (overnight)

________________________________________________________________________________________________________________________________________________


EAST LOT – WORK ZONE

RUE SAINTE-CATHERINE OUEST, BETWEEN RUE SAINT-ALEXANDRE AND RUE DE BLEURY
The work schedule may change, depending on the weather conditions and unforeseen circumstances.


Corner of Rue Saint-Alexandre

Nature of the work: installation of water mains
Expected impact: excavator noise
Dates and schedule: March 29, 30, 31, April 1 and 2 (around the clock)

Nature of the work: watertightness test on the water mains
Expected impact: none
Dates and schedule: April 3 (around the clock)

Nature of the work: chlorination of the water supply system
Expected impact: none
Dates and schedule: April 4 (around the clock)

Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, sawing
Dates and schedule: April 3 and 4 (6 a.m. to 3 p.m.)


Between Rue Saint-Alexandre and Rue De Bleury

Nature of the work: demolition and reconstruction of underground telecommunications infrastructures
Expected impacts: hydraulic drilling, sawing
Dates and schedule: March 29, 30 and 31 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.)

Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, sawing
Dates and schedule: April 1, 2, 3 and 4 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.)

Nature of the work: test trenches for soil sampling
Expected impact: excavator noise
Dates and schedule: March 29 (overnight)

Corner of Rue De Bleury

Nature of the work: abandonment of an underground water main – concrete filling
Expected impact: excavator noise
Dates and schedule: March 29 (around the clock)

Nature of the work: test trenches for soil sampling
Expected impact: excavator noise
Dates and schedule: March 29 (overnight)

Nature of the work: reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, sawing
Dates and schedule: April 1, 2, 3 and 4 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.)

___________________________________________________________________________________________________________________________


STAY INFORMED

Have a question you would like to ask?

Contact our liaison officers between 7:30 a.m. and 9 p.m. at 514-867-9339 or
stecatherineouest@ville.montreal.qc.ca

FACILITATE YOUR TRAVEL

Mobilité Montréal

PARKING NEAR THE WORK SITE

Valet service
Drop-off locations are on the corner of Rue Sainte-Catherine Ouest and Rue Mansfield (west), and on the corner of Boulevard De Maisonneuve and Rue De Bleury (north).

City Parkingapplication
Reserve a private parking space, underground or outdoors, at a preferential rate.

Delivery zones

___________________________________________________________________________________________________________________________


Other work sites and work operations in the area

Info-travaux (Ville-Marie), click here (in French only)
REM (future McGill station), click here