Work operations planned from April 15 to 18, 2019

2 months ago

SAINTE-CATHERINE OUEST PROJECT

  • Reconstruction of underground infrastructures
  • Phase 1, lot 1 A: between Boulevard Robert-Bourassa and Rue De Bleury
  • From February 11 until the fall of 2019. Development work from 2019 to 2020
  • Work schedule: 24/7, unless indicated otherwise

    All businesses will remain open during the work operations.



WEST LOT – WORK ZONE

RUE SAINTE-CATHERINE OUEST, BETWEEN BOULEVARD ROBERT-BOURASSA AND RUE SAINT-ALEXANDRE

The work schedule may change, depending on the weather conditions and unforeseen circumstances.


Corner of Boulevard Robert-Bourassa


Nature of the work: sewer reconstruction and installation of secondary water mains
Expected impact: excavator noise, sawing, nailing
Dates and schedule: April 15 (6 p.m. to 1:30 a.m.) 16, 17, 18 (around the clock)

East of Boulevard Robert-Bourassa

Nature of the work: reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, excavation, sawing
Dates and schedule: April 15 to 18 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.)

Between Boulevard Robert-Bourassa and Place Phillips

Nature of the work: watertightness tests and chlorination of the water supply system
Expected impacts: none
Dates and schedule: April 15 to 18 (days only)

Corner of Rue Union (south side)

Nature of the work: reconstruction of underground electrical infrastructures
Expected impacts: wood sawing, nailing
Dates and schedule: April 15 to 18 (6 a.m. to 3 p.m. – 3:30 p.m. to 12:30 a.m.)

Between Rue Union and Place Phillips

Nature of the work: lining of a gas main
Expected impact: sanding noise
Dates and schedule: April 15 to 18 (around the clock)

________________________________________________________________________________________________________________________________________________


EAST LOT – WORK ZONE

RUE SAINTE-CATHERINE OUEST, BETWEEN RUE SAINT-ALEXANDRE AND RUE DE BLEURY
The work schedule may change, depending on the weather conditions and unforeseen circumstances.


Corner of Rue Saint-Alexandre

Nature of the work: demolition and reconstruction of underground electrical infrastructures
Expected impacts: hydraulic drilling, sawing
Dates and schedule: April 15 to 18 (6 a.m. to 3 p.m.)

Between Rue Saint-Alexandre and Rue De Bleury

Nature of the work: water service interruption and commissioning of the secondary water main
Expected impact: water service interruption
Dates and schedule: overnight from April 15 to 16 and overnight from April 16 to 17
**Door hangers will be placed 48 hours in advance to notify building occupants.**

Nature of the work: connection of water service inlets
Expected impact: brief water service interruptions
Dates and schedule: April 16, 17, 18, 19 (overnight)
**Door hangers will be placed 48 hours in advance to notify building occupants.**

___________________________________________________________________________________________________________________________


STAY INFORMED

Have a question you would like to ask?

Contact our liaison officers between 7:30 a.m. and 9 p.m. at 514-867-9339 or
stecatherineouest@ville.montreal.qc.ca

FACILITATE YOUR TRAVEL

Mobilité Montréal

PARKING NEAR THE WORK SITE

Valet service
Drop-off locations are on the corner of Rue Sainte-Catherine Ouest and Rue Mansfield (west), and on the corner of Boulevard De Maisonneuve and Rue De Bleury (north).

City Parkingapplication
Reserve a private parking space, underground or outdoors, at a preferential rate.

Delivery zones

___________________________________________________________________________________________________________________________


Other work sites and work operations in the area

Info-travaux (Ville-Marie), click here (in French only)
REM (future McGill station), click here